Applications of Semidefinite Optimization in Stochastic Project Scheduling
Author(s)
Bertsimas, Dimitris J.; Natarajan, Karthik; Teo, Chung Piaw
DownloadHPCES002.pdf (121.7Kb)
Metadata
Show full item recordAbstract
We propose a new method, based on semidefinite optimization, to find tight upper bounds on the expected project completion time and expected project tardiness in a stochastic project scheduling environment, when only limited information in the form of first and second (joint) moments of the durations of individual activities in the project is available. Our computational experiments suggest that the bounds provided by the new method are stronger and often significant compared to the bounds found by alternative methods.
Date issued
2002-01Series/Report no.
High Performance Computation for Engineered Systems (HPCES);
Keywords
project scheduling, problem of moments, semidefinite programming, co-positivity, tardiness